GUT ALTENHOF Biogas Plant
Location | Germany |
Construction Period | 2007 |
Input | Corn silage, wheat silage, grass silage |
Fermenter | Concrete Tank 1,500 m3 |
Gas utilization | Gas engine 365 kWel |
Extension | 2012/13: Second CHP and heat grid to the swimming pool; new heat distribution system 2021: Storage tank |
Specials | Digester, secondary digester and storage tank with gas holder roof, thermophilic operation |
Responsibility | Basic evaluation, pre-, draft-, approval and execution planning, tendering, participating in contract awarding process, site management/project controlling, start-up |