FALKENSTEIN Biogas Plant

LocationGermany
Construction Period2008
InputCorn silage, whole crop silage, sweet sorghum silage
FermenterSteel tank 2 x 3,100 m3
Gas utilizationGas engine 2 x 716 kW
SpecialsTwo digester, gas holder above secondary digester, thermophilic operation, heat usage
ResponsibilityBasic evaluation, pre-, draft- and execution planning, tendering, participating in contract awarding process, site management/project controlling, start-up