NEW YORK STATE 1 Biogas Plant

Location USA, New York (state)
Construction Period 2022
Input Dairy manure
Fermenter Existing digester
Gas utilization Biogas upgrading system 450m³/h
Extension Extention of existing agricultural biogas plant, virtual gas pipeline (by truck), digestate heat recovery
Specials  
Responsibility Basic evaluation, pre-, draft- and executationplaning, tendering, participating in contract awarding process, site management/project controlling, start-up, training for operator