JCBE DERBY Biogas Plant
Location | UK, Derby |
Construction Period | 2017/2018 |
Input | Hydrolised Kitchen Cat. 2 (viscera)-, paper and cardboard waste (treated by TPH), water (recycled, rain, mains) |
Fermenter | Concrete tank, 2 x 5,300 m³ |
Gas utilization | Gas-upgrading system |
Specials | Pretreament system: Thermal Pressure Hydrolysis (TPH) for input material, cooling tank with central agitator for reception of hot input material, substrate cooling system, two storage tanks, two digester and one secondary digester - all equipped with double membrane gas holder roof, biogas upgrading system |
Responsibility | Basic evaluation, pre-, draft- and execution planning, tendering, participating in contract awarding process, site management/project controlling, start-up, operator training and instruction |
Datasheet | Datasheet JCBE DERBY |